⚠️ Superseded figures. The slides below were built for the previous 1,010-bus reduction (March 2026) and their dollar/GW numbers are out of date. The current production pipeline uses a 1,304-bus subgraph Ward reduction (3,626 equivalent lines). Current total CEP cost (DCOPF, corrected re-run 2026-06-15): Low $182B · Ref $295B · High $629B (VoLL $9,000/MWh; shedding 662 MWh / 1,804 MWh / 0.93 TWh). See the main page and the live React dashboard for authoritative results.

SPP Capacity Expansion Planning

Ward-Reduced Network Model & Scenario Analysis

Ali Jahanbani Ardakani, Charlie Philips, James McCalley
Iowa State University — April 1, 2026

Press → or Space to advance

Why This Work?

The Challenge

  • The Eastern Interconnection model: 96,328 buses, 80,000+ branches
  • Direct capacity expansion on this scale is computationally infeasible
  • Need a reduced equivalent that preserves electrical fidelity
  • Must support DC optimal power flow formulation

SPP Load Growth Context

From SPP's published ITP studies:

  • FERC 714 SPP 2024 peak: 54 GW
  • SPP 2025 ITP: 70–83 GW by 2034
  • SPP 2026 ITP: 91–110 GW by 2035
  • Driven by data centers, electrification, reshoring

Our model: 2024 ITP base case + FERC 714 → 2049

Data Sources

Network, Generation & Load

  • PSS/E 2024 ITP: Full Eastern Interconnection study case — buses, branches, transformers, and 596 generators with capacity and fuel type
  • Generator technologies: Mapped from PSS/E fuel codes to 7 categories (Coal, CC Gas, Gas CT, Wind, Solar, Nuclear, Hydro)
  • FERC 714: 8,760 hourly SPP system load (2024)
  • Bus locations: 90,455 buses geocoded (OSM + HIFLD)

Cost & Fuel

  • NREL ATB 2024: OCC, FOM, VOM, heat rates by technology (Moderate scenario)
  • EIA AEO 2025: Fuel price projections (Reference case)

Renewable Resources

  • NREL 2024 supply curves: Wind + Solar sites mapped to buses
  • 9,942 wind sites → 1,004 buses
  • 10,604 solar sites → 1,057 buses

Weather-Derived Capacity Factors

  • HRRR reanalysis: Location-specific wind and solar output
  • Wind avg CF: 0.415
  • Solar avg CF: 0.25 (including nighttime)

Pipeline

PSS/E RAW
96K buses
Ward Reduction
1,763 buses
Load Analysis
FERC 714
Equivalent Line
Capacities
7,134 lines
CEP Model
DCOPF
Results

Key Steps

  • Ward reduction: Preserves electrical coupling at the SPP boundary
  • Equivalent line capacities: 7,134 thermal limits estimated for reduced network lines
  • HRRR capacity factors: Location-specific wind and solar from weather reanalysis

Runtime (per scenario)

StageTime
Network reduction5 min
Line capacity estimation25 min
CEP model solve~60 min
Total~90 min

Ward Network Reduction

Method

Partition the admittance matrix into retained and eliminated buses:

Yeq = Yrr - Yre · Yee-1 · Yer
  • 98.2% reduction: 96,328 → 1,763 buses
  • Perfect load conservation at retained buses
  • External boundary buses provide realistic coupling

Retained Network

MetricValue
Retained buses1,763
SPP internal~1,020
Transit corridors~110
External boundary~630
Equivalent lines7,134
Generators596
SPP+Transit load85,627 MW

Capacity Expansion Model

Formulation

  • Linear program minimizing total discounted cost
  • DC optimal power flow with angle coupling
  • 6 planning years × 17 time blocks
  • 15% planning reserve margin
  • Carbon reduction: 2%/year → 50% by 2049

Cost Components

  • Generation investment
  • Transmission expansion
  • Fixed & variable O&M
  • Fuel cost

Technologies

TechnologyCan Build?Can Retire?Capacity Credit
CC GasYesYes1.00
Gas CTYesYes1.00
WindYesYes0.20
SolarYesYes0.35
CoalNoYes1.00
NuclearNoYes0.90
HydroNoYes0.50

Capacity credit = how much each GW counts toward the 15% reserve margin.

Load Growth Scenarios

1.5%
Low Growth — historical trend

2034: 96 GW | 2049: 116 GW

4.0%
Reference — data centers + electrification

2034: 118 GW | 2049: 197 GW

7.0%
High Growth — aggressive electrification

2034: 150 GW | 2049: 382 GW

Alignment with SPP ITP Projections

SPP 2025 ITP projects 70–83 GW by 2034 (our low scenario: 96 GW in 2034).
SPP 2026 ITP projects 91–110 GW by 2035 (between our low and reference scenarios).
Our reference (4%) and high (7%) represent accelerated growth scenarios driven by large load interconnection.

Results — Total SPP System Cost

All scenarios DCOPF optimal, zero unserved energy

LowRefHigh
Total (B$)$117$207$431
Gen Investment$30$83$205
Line Investment$4$5$13
Fixed O&M$67$90$142
Fuel$13$24$59

Cost Breakdown — Reference

FOM
$90B
43%
GenInv
$83B
40%
Fuel
$24B
11%
LineInv
$5B
3%

Gen investment increases 7x from low ($30B) to high ($205B). Transmission investment remains relatively stable.

Generation Investment by Scenario

New capacity built through 2049

Low (1.5%) — 48 GW new

GasCT
31 GW
65%
Wind
11 GW
22%
Solar
5 GW
11%
CC
1 GW
2%

Reference (4%) — 182 GW new

Wind
75 GW
41%
GasCT
72 GW
40%
Solar
20 GW
11%
CC
15 GW
8%

High (7%) — 543 GW new

Wind
252 GW
46%
GasCT
149 GW
27%
Solar
102 GW
19%
CC
40 GW
7%

Key Insight

At low growth, Gas CT dominates (65%) — firm capacity is the priority. As growth increases, wind takes the lead (41-46%) due to its high capacity factor (0.415 avg). Gas CT remains essential for firm capacity because wind's capacity credit is only 0.20 — requiring ~5 GW of gas peaking for every 1 GW of effective firm capacity from wind.

Limitations & Future Work

Current Limitations

  • Single weather year — 2024 HRRR data only
  • Uniform load profile — All buses follow same FERC 714 shape
  • No storage cycling constraints
  • No forced retirement schedule — Economic retirement only
  • Ward load leakage — ~4% of SPP load redistributes to external buses

Planned Improvements

  • Adaptive Capacity Expansion (ACEP) — Multi-stage stochastic formulation with uncertainty in load, fuel prices, and policy
  • Storage constraints — SOC limits, charge/discharge, round-trip efficiency
  • Sensitivity analysis — Carbon policy, discount rate, technology costs
  • Multi-year weather validation
  • Improved network reduction — Target ~1,500 buses for faster solves

Sensitivity: What If SPP Is Islanded?

Remove external buses — SPP must self-supply entirely

With Eastern Interconnection (1,763 buses)

LowRefHigh
Total (B$)$117$207$431
Unserved Energy000

SPP Island — no external (1,193 buses)

LowRefHigh
Total (B$)$155$267$524
Unserved Energy~0270 GWh4,055 GWh

Costs exclude load shedding penalty.

Key Insight

  • At 1.5% growth, SPP can nearly self-supply — cost increases 33% without interconnection
  • At 4%+ growth, external transmission paths are essential — transit corridors cannot serve growing load without external routing
  • The value of interconnection increases dramatically with load growth

Summary

96K → 1.8K
buses (98.2% reduction)
$117–431B
SPP system cost (25-year NPV)
Wind #1
75 GW new wind in reference case

Key Takeaways

  • Ward reduction produces a tractable, electrically faithful equivalent
  • Load growth drives $117B to $431B in total SPP system cost
  • Wind dominates new investment at higher growth rates (HRRR CF = 0.415)
  • Gas CT is essential for firm capacity due to low wind capacity credit
  • As growth increases, investment shifts from firm gas → renewables + gas

Questions?